I need a solution
Hi,
i have following Job config..
ServerA:
Backup 2 Disk SQL - 8:00 pm
Backup 2 Disk inc (log) - 8:00 pm
The problem is that the log backup never runs, only if i start it manually. Is it because they are scheduled at the same time? When i config the Job with 1 hour time difference both jobs run successfully.
Works as designed or problem?
Thanks and Regards